March 25, 2026. Road Traffic Management Center
🚦 Smart Traffic Lights:
On Bobur Street, anchor blocks for traffic light support poles were installed at 4 sites — a total of 25 anchor blocks. On Sebzor Street, at 1 site, 10 support poles were installed and 32 traffic lights were put into operation. On KXAY Street, 30 traffic lights were installed and commissioned; additionally, 4 anchor blocks for support poles were installed at 2 sites. On Mahtumquli Street, 28 anchor blocks for support poles were installed at 2 sites. On Ahmad Donish Street, at 1 site, 59 meters of plastic pipe were laid, and at another site, 10 support poles were installed. On the Nurafshon direction, at 1 site, a 15-meter trench for cable was excavated, and at another site, 10 anchor blocks were installed.
🛣 Current Repair Works: Today, milling works were carried out on an area of 2,220 square meters. This includes 200 sq.m in Olmazor district and 2,020 sq.m in areas under the Central Streets Department.
In addition, asphalt laying works were performed on 8,720 square meters. This includes:
- 2,150 sq.m in Mirobod district,
- 1,926 sq.m in Yashnabad district,
- 1,114 sq.m in Yunusabad district,
- and 3,530 sq.m in areas under the Central Streets Department.
🚧 Road Markings and Signs: 1,200 meters of road markings were applied on Sebzor Street and 700 meters on Mehr Street. In total, 1,900 meters of markings were renewed between 00:00 and 06:00 at night.
Additionally, 87 new road signs were installed.
🚏 Bus Stop Upgrades: Bus stop structures were installed as follows: 1 on Buyuk Ipak Yuli Street, 1 on Bobur Street, 4 on Bunyodkor Street, and 1 on Sebzor Street. Two platforms were also constructed.
Currently, installation works are ongoing for 15 bus stops: 6 on Buyuk Ipak Yuli Street, 3 on Mahtumquli Street, 1 on Osiyo Street, 2 on Mirzo Ulugbek Street, 2 on Istiqbol Street, and 1 on KXAY Street.

⏺ Take a look at the results of large-scale works carried out over the past 24 hours:🚦 Smart Traffic Lights: On Farg‘o...

🗑 March 30 was designated by the United Nations as the International Day of Zero Waste. This day is aimed at reducing w...

For this purpose, 204.7 billion soums have been allocated.Of which: — 112 projects — construction works — 54 projects ...